Bill of Quantities Example
From Drawing to BOQ

A small bill of quantities worked out step by step from two drawings, with every calculation shown. Includes a filled example, a blank Excel template, and the mistakes AutoBOQ made on the same drawings.

Published
Updated
Plan of the example garden room beside four quantities from its bill: floor, skirting, walls and ceiling

A bill of quantities (BOQ) lists the work in a construction job. Each item has a description, a unit and a quantity. Add a rate to each item, and you can work out its cost.

This example covers the finishes, doors and windows for one garden room. It shows how each quantity comes from the drawings, so you can check it yourself.

We made up this project for learning. The quantities follow the notes on its drawings. They haven't been measured to NRM2 or another standard method, or checked by a quantity surveyor. Don't use them for construction, tendering or pricing.

Download the example and template

The drawings

Plan of the example garden room: 5000 by 4000 mm inside, with door D01, windows W01 and W02, and notes for the floor, skirting, ceiling and walls.

Drawing A-101. Drawing A-201 gives the ceiling height and the sizes of the door and windows.

These details decide the quantities:

Detail Where it is
Room is 5.00 m by 4.00 m inside A-101
Floor to ceiling is 2.40 m A-201 section
D01 is 1.80 m by 2.10 m A-201 schedule
W01 and W02 are each 1.20 m by 1.00 m A-201 schedule
No skirting at D01 A-101, note 4
Openings are deducted from wall finishes A-201, note 1
Door and window reveals aren't included in wall finishes A-101, note 7
Slab, roof and external walls stay as they are A-201
Electrical work is by others A-201, note 3

The plan also gives the outside size, 5.60 m by 4.60 m. Using that for the floor would give 25.76 m² instead of 20.00 m². The notes say that internal dimensions are to the face of the plaster, so use the inside size for the finishes.

Work out each quantity

Floor, ceiling and skirting

The floor and ceiling are each 5.00 by 4.00, or 20.00 square metres. The skirting is twice 5.00 plus 4.00, less the 1.80 metre door, or 16.20 metres.

  • Floor: 5.00 × 4.00 = 20.00 m²
  • Ceiling: 5.00 × 4.00 = 20.00 m²
  • Skirting: 2 × (5.00 + 4.00) − 1.80 = 16.20 m

The skirting runs under the windows, so only the door is deducted.

Walls

The four walls laid flat: 43.20 square metres in total, less 6.18 square metres of openings, leaves 37.02 square metres.

  1. All four walls: 2 × (5.00 + 4.00) × 2.40 = 43.20 m²
  2. Door D01: 1.80 × 2.10 = 3.78 m²
  3. Windows W01 and W02: 2 × 1.20 × 1.00 = 2.40 m²
  4. Wall finish: 43.20 − 3.78 − 2.40 = 37.02 m²

Skim and paint cover the same area, but they're different work, so each gets its own item.

The finished bill of quantities

Item Description Unit Quantity
1 D01: aluminium French doors, double glazed, 1800 × 2100 mm. Supply and fit, including ironmongery nr 1
2 W01: aluminium casement window, double glazed, 1200 × 1000 mm. Supply and fit, including ironmongery nr 1
3 W02: aluminium casement window, double glazed, 1200 × 1000 mm. Supply and fit, including ironmongery nr 1
4 F1: 14 mm engineered oak boards on 3 mm underlay m² 20.00
5 S1: 18 × 120 mm painted MDF skirting, including its paint finish m 16.20
6 P1: skim finish to internal walls m² 37.02
7 C1: 12.5 mm plasterboard and skim ceiling m² 20.00
8 P1: one mist coat and two full coats of emulsion to walls m² 37.02
9 C1: one mist coat and two full coats of emulsion to ceiling m² 20.00

Here, "nr" means number. The quantities don't include an allowance for waste.

The filled spreadsheet also gives the drawing reference for each item and has a column for who checked it. The rates are blank. Example prices could be mistaken for current ones, so use rates that suit your own job.

List what isn't included

The spreadsheet has a separate sheet for work that isn't measured or priced:

  • The existing slab, roof and external walls
  • Electrical work, which is by others
  • Wall finishes to door and window reveals
  • Floor boards in door reveals

This shows that each one was noticed and left out on purpose. It also makes it less likely that someone will price it by mistake.

What AutoBOQ got right and wrong

We ran the same two drawings five times through AutoBOQ, our tool for turning PDF drawings into a bill of quantities to review. At the time, it used OpenAI's GPT-5.5 model. All five runs gave the right quantity for the nine items above. The first two runs also made mistakes that someone would need to find:

Mistake Why it matters Correction
Run 1 added a separate item for painting the skirting Item 5 already includes the paint, so it could be priced twice Remove the extra item
Run 2 measured the existing roof as 25.76 m², the slab as 20 m² and the external walls as 20.4 m The drawings say all three stay as they are Move them to "Not in scope" with no quantity
Run 2 gave electrical work a quantity of 1 The drawings say it's by others Move it to "Not in scope" with no quantity

We then changed AutoBOQ in two ways:

  1. Its instructions now say how to handle work that isn't part of the job and tell it not to list the same finish twice.
  2. If an item is listed as "Not in scope", our code removes any quantity and doesn't add a price.

The next three runs gave the same nine work items, with no extra skirting item. Work that wasn't part of the job had no quantity, and the run with pricing didn't price it. The list of excluded work still changed slightly: two runs also listed the door and window reveals, and one didn't. The AI still has to put each item in the right place, so someone still needs to check the bill.

AutoBOQ now uses a newer model, GPT-6.2 Sol, and reads each page in more detail. We tested that setup four more times on the same drawings. Two runs used the whole tool, with prices. The other two only read the drawings and organised the items, using the same instructions and checks. All four gave the right quantity for the nine items and had no extra skirting item. Work that wasn't part of the job had no quantity, and neither run with pricing priced it. The list of excluded work still changed between runs. Because we changed the model and the page detail together, these runs don't compare the two models alone.

Nine runs on one simple drawing set can't tell you how accurate AutoBOQ is. Your drawings could include unclear scans, missing dimensions, several revisions or clashing notes.

How to check a bill of quantities

  1. Check the revision. Make sure every quantity comes from the latest drawings.
  2. Trace each item back to a drawing, schedule or note.
  3. Redo the calculation. Check whether it uses the inside or outside size, and which openings it deducts.
  4. Look for double counting, especially where an item already includes its finish.
  5. Look for missing work. Go through the drawings one note at a time. Checking only the bill won't show you what's missing.
  6. Check what's excluded, including retained work and work by others.
  7. Record who checked each item, and what they changed.

How to use the blank template

  1. On Bill of quantities, give each item a number, section, description and unit.
  2. On Measurements, use the same number for each line that belongs to that item.
  3. Enter lengths in metres. For counted items, such as doors, leave the length and the width or height blank. Use -1 to deduct an opening.
  4. The bill adds up the lines for each item. When you enter a rate, it works out the amount.
  5. Before you use the total, make sure Items still without a rate is zero.

Agree how the work will be measured before you start. In the UK, RICS publishes the New Rules of Measurement. This template doesn't apply those rules for you. For a real tender, ask a qualified quantity surveyor to check the method and quantities.

Try it with your own drawings

You can request an AutoBOQ access code and compare its results with a bill you've already checked. Our guide to AI in construction explains where AI can help and where it can't. If you're comparing products, see our guide to construction estimating software.

Related notes

View all
  1. AI Development

    Production-Ready AI Agents: Architecture Patterns That Survive Real Users

    Learn how to build AI agents that work beyond demos. Covers orchestration, tool boundaries, error recovery, evaluation, and deployment tradeoffs.
  2. AI Development

    AI Product Development: From Workflow Opportunity to Production

    A practical guide for business and product leaders turning a valuable workflow into an AI product that users can trust, operate, and improve.
  3. AI Engineering

    AI Internal Tools: Three Reliability Problems and How We Fixed Them

    AI can build an internal tool quickly, but people also need to be able to rely on it. Here are three problems we fixed while building an internal app builder, and the tests you can use to look for them.

Start with one workflow.

Tell us which piece of work you’d like AI to take on. We’ll reply with what a system could do, what it should leave to a person, and what a first version would take to build.