A bill of quantities (BOQ) lists the work in a construction job. Each item has a description, a unit and a quantity. Add a rate to each item, and you can work out its cost.
This example covers the finishes, doors and windows for one garden room. It shows how each quantity comes from the drawings, so you can check it yourself.
We made up this project for learning. The quantities follow the notes on its drawings. They haven't been measured to NRM2 or another standard method, or checked by a quantity surveyor. Don't use them for construction, tendering or pricing.
Download the example and template
- Filled bill of quantities: the finished example, with its calculations as Excel formulas
- Blank bill of quantities template: space for 40 items and 200 measurement lines
- Drawings: the two sheets used in this example
The drawings

Drawing A-101. Drawing A-201 gives the ceiling height and the sizes of the door and windows.
These details decide the quantities:
| Detail | Where it is |
|---|---|
| Room is 5.00 m by 4.00 m inside | A-101 |
| Floor to ceiling is 2.40 m | A-201 section |
| D01 is 1.80 m by 2.10 m | A-201 schedule |
| W01 and W02 are each 1.20 m by 1.00 m | A-201 schedule |
| No skirting at D01 | A-101, note 4 |
| Openings are deducted from wall finishes | A-201, note 1 |
| Door and window reveals aren't included in wall finishes | A-101, note 7 |
| Slab, roof and external walls stay as they are | A-201 |
| Electrical work is by others | A-201, note 3 |
The plan also gives the outside size, 5.60 m by 4.60 m. Using that for the floor would give 25.76 m² instead of 20.00 m². The notes say that internal dimensions are to the face of the plaster, so use the inside size for the finishes.
Work out each quantity
Floor, ceiling and skirting

- Floor: 5.00 × 4.00 = 20.00 m²
- Ceiling: 5.00 × 4.00 = 20.00 m²
- Skirting: 2 × (5.00 + 4.00) − 1.80 = 16.20 m
The skirting runs under the windows, so only the door is deducted.
Walls

- All four walls: 2 × (5.00 + 4.00) × 2.40 = 43.20 m²
- Door D01: 1.80 × 2.10 = 3.78 m²
- Windows W01 and W02: 2 × 1.20 × 1.00 = 2.40 m²
- Wall finish: 43.20 − 3.78 − 2.40 = 37.02 m²
Skim and paint cover the same area, but they're different work, so each gets its own item.
The finished bill of quantities
| Item | Description | Unit | Quantity |
|---|---|---|---|
| 1 | D01: aluminium French doors, double glazed, 1800 × 2100 mm. Supply and fit, including ironmongery | nr | 1 |
| 2 | W01: aluminium casement window, double glazed, 1200 × 1000 mm. Supply and fit, including ironmongery | nr | 1 |
| 3 | W02: aluminium casement window, double glazed, 1200 × 1000 mm. Supply and fit, including ironmongery | nr | 1 |
| 4 | F1: 14 mm engineered oak boards on 3 mm underlay | m² | 20.00 |
| 5 | S1: 18 × 120 mm painted MDF skirting, including its paint finish | m | 16.20 |
| 6 | P1: skim finish to internal walls | m² | 37.02 |
| 7 | C1: 12.5 mm plasterboard and skim ceiling | m² | 20.00 |
| 8 | P1: one mist coat and two full coats of emulsion to walls | m² | 37.02 |
| 9 | C1: one mist coat and two full coats of emulsion to ceiling | m² | 20.00 |
Here, "nr" means number. The quantities don't include an allowance for waste.
The filled spreadsheet also gives the drawing reference for each item and has a column for who checked it. The rates are blank. Example prices could be mistaken for current ones, so use rates that suit your own job.
List what isn't included
The spreadsheet has a separate sheet for work that isn't measured or priced:
- The existing slab, roof and external walls
- Electrical work, which is by others
- Wall finishes to door and window reveals
- Floor boards in door reveals
This shows that each one was noticed and left out on purpose. It also makes it less likely that someone will price it by mistake.
What AutoBOQ got right and wrong
We ran the same two drawings five times through AutoBOQ, our tool for turning PDF drawings into a bill of quantities to review. At the time, it used OpenAI's GPT-5.5 model. All five runs gave the right quantity for the nine items above. The first two runs also made mistakes that someone would need to find:
| Mistake | Why it matters | Correction |
|---|---|---|
| Run 1 added a separate item for painting the skirting | Item 5 already includes the paint, so it could be priced twice | Remove the extra item |
| Run 2 measured the existing roof as 25.76 m², the slab as 20 m² and the external walls as 20.4 m | The drawings say all three stay as they are | Move them to "Not in scope" with no quantity |
| Run 2 gave electrical work a quantity of 1 | The drawings say it's by others | Move it to "Not in scope" with no quantity |
We then changed AutoBOQ in two ways:
- Its instructions now say how to handle work that isn't part of the job and tell it not to list the same finish twice.
- If an item is listed as "Not in scope", our code removes any quantity and doesn't add a price.
The next three runs gave the same nine work items, with no extra skirting item. Work that wasn't part of the job had no quantity, and the run with pricing didn't price it. The list of excluded work still changed slightly: two runs also listed the door and window reveals, and one didn't. The AI still has to put each item in the right place, so someone still needs to check the bill.
AutoBOQ now uses a newer model, GPT-6.2 Sol, and reads each page in more detail. We tested that setup four more times on the same drawings. Two runs used the whole tool, with prices. The other two only read the drawings and organised the items, using the same instructions and checks. All four gave the right quantity for the nine items and had no extra skirting item. Work that wasn't part of the job had no quantity, and neither run with pricing priced it. The list of excluded work still changed between runs. Because we changed the model and the page detail together, these runs don't compare the two models alone.
Nine runs on one simple drawing set can't tell you how accurate AutoBOQ is. Your drawings could include unclear scans, missing dimensions, several revisions or clashing notes.
How to check a bill of quantities
- Check the revision. Make sure every quantity comes from the latest drawings.
- Trace each item back to a drawing, schedule or note.
- Redo the calculation. Check whether it uses the inside or outside size, and which openings it deducts.
- Look for double counting, especially where an item already includes its finish.
- Look for missing work. Go through the drawings one note at a time. Checking only the bill won't show you what's missing.
- Check what's excluded, including retained work and work by others.
- Record who checked each item, and what they changed.
How to use the blank template
- On Bill of quantities, give each item a number, section, description and unit.
- On Measurements, use the same number for each line that belongs to that item.
- Enter lengths in metres. For counted items, such as doors, leave the length and the width or height blank. Use
-1to deduct an opening. - The bill adds up the lines for each item. When you enter a rate, it works out the amount.
- Before you use the total, make sure Items still without a rate is zero.
Agree how the work will be measured before you start. In the UK, RICS publishes the New Rules of Measurement. This template doesn't apply those rules for you. For a real tender, ask a qualified quantity surveyor to check the method and quantities.
Try it with your own drawings
You can request an AutoBOQ access code and compare its results with a bill you've already checked. Our guide to AI in construction explains where AI can help and where it can't. If you're comparing products, see our guide to construction estimating software.